1What is PHA?
L'Preliminary Hazard Analysis (PHA) systematically identifies facility hazards early in a project's or operation's lifecycle. It reviews every system or item of equipment to list what could go wrong, without seeking FMEA's exhaustiveness or LOPA's quantitative precision. It is a structured first pass and often the gateway to more detailed methods for the most critical scenarios.
2Definitions
| Term | Definition |
|---|---|
| Hazard | An inherent property of equipment or a substance that can cause harm, such as stored mechanical energy, a toxic substance, or electrical voltage. A hazard exists independently of any incident; it is a potential, not an event. |
| Hazardous event | The abnormal situation that would materialise the hazard, such as rupture of a pump casing. It is the shift from potential to incident. |
| Cause | What may lead to the hazardous event, such as prolonged cavitation or internal corrosion. |
| Consequence | What results if the hazardous event occurs, such as projected metal fragments or flooding of the room. |
In practice, the Hazard field is often completed using broad categories to facilitate classification and statistics: Mechanical (rupture, projection, crushing), Chemical (leak, toxicity, reaction), Electrical (short circuit, electric shock), Thermal, Ergonomique…
3Before starting: model the system
Like FMEA, PHA relies on an initial breakdown of the facility into systems and items of equipment — voir la notion transverse Facility modelling, shared by PHA, FMEA, HAZOP, and Bow-Tie.
4Method steps
- Break down the facility into systems or items of equipment (see modelling above).
- Identify the hazard associated with each item of equipment (energy, substance, movement, etc.).
- Describe the hazardous event : the abnormal situation that would materialise the hazard.
- List the causes that may lead to the event.
- List the consequences for people, the environment, and property.
- Rate the scenario en severity level and probability, avant mesures (voir section suivante).
- List existing and planned measures, then rate the scenario again after measures.
5Rate risk in PHA
The general principles for rating risk—matrix, scales, and before/after measures—are shared by all methods. See the cross-cutting concept Rate a risk. PHA combines two metrics, each rated from 1 to 4 in Polyodos:
Severity
| Level | Label | Signification |
|---|---|---|
| 1 | Negligible | First aid with no time off work |
| 2 | Significative | Partial temporary incapacity under three days |
| 3 | Grave | Partial permanent incapacity or hospitalisation over one day |
| 4 | Catastrophique | Death or total permanent incapacity |
Probability (likelihood)
| Level | Label | Indicative frequency |
|---|---|---|
| 1 | Highly unlikely | < 10⁻⁴ / an |
| 2 | Unlikely | 10⁻⁴ – 10⁻² / an |
| 3 | Likely | 1 occurrence possible par an |
| 4 | Frequent | Plusieurs occurrences attendues |
Criticality matrix
Criticality results from combining Severity × Probability in a configurable matrix, producing a four-level scale:
| Level | Label | Signification |
|---|---|---|
| 1 | Acceptable | Maintenir la vigilance |
| 2 | Monitor | Planned treatment |
| 3 | Non acceptable | Short-term treatment required |
| 4 | Inacceptable | Urgent treatment; stop if necessary |
6Existing and planned measures
Each scenario distinguishes existing measures (already in place and considered in the before-measures rating, often blank when the scenario is not yet covered) from planned measures (the action plan, whose implementation justifies the after-measures rating). This uses the same distinction between prevention / protection qu'en AMDEC :
| Type | Acts on | Exemples |
|---|---|---|
| Prevention | Probability | Periodic vibration monitoring, visual inspection, preventive replacement of wear parts, and procedures governing hazardous operations (work permit) |
| Protection | Severity / detection | Gas detector with alarm and automatic shutdown, residual-current device, and thermal protection |
7Example completed in Polyodos
The Polyodos demonstration dataset for a drinking-water treatment plant covers four scenarios across Pumping, Chemical Treatment, and Storage systems:
| # | System / Equipment | Hazard | Causes | Hazardous event | Consequences | G | P | C | Planned measures | G' | P' | C' |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pompage — Pompe centrifuge P-101 | Mechanical | Prolonged cavitation, excessive vibration, internal corrosion | Rupture de la volute de pompe | Projected metal fragments, flooding of the pump room, production shutdown | G4 | P2 | R3 | Monthly vibration monitoring (piezo sensors), replacement of mechanical seals every two years | G3 | P1 | R2 |
| 2 | Traitement chimique — Cuve chlore CL-301 | Chemical | HDPE wall corrosion, rupture of the filling connection, overpressure during unloading | Fuite de chlore liquide | Toxic atmosphere (chlorine gas), severe respiratory irritation, site evacuation | G5 | P2 | R? | Chlorine-gas detector with audible alarm and automatic shutdown, unloading procedure with work permit, annual tank inspection | G4 | P1 | R2 |
| 3 | Pumping — Electric motor M-101 | Electrical | Wiring degraded by moisture, prolonged motor overload, circuit-breaker failure | Short circuit causing a switchboard fire | Electrical-room fire, loss of pumping power, operator electric-shock risk | G3 | P2 | R2 | Annual electrical-installation inspection, 30 mA residual-current device, and motor thermal protection | G2 | P1 | R1 |
| 4 | Storage — Treated-water tank CS-301 | Mechanical | Reinforced-concrete ageing, differential ground settlement, hydraulic overpressure | Concrete tank rupture (structural crack) | Major overflow (500 m³), downstream flooding, groundwater contamination | G4 | P1 | R2 | Quarterly visual inspection (cracks and deformation), geotechnical ground assessment every ten years | G3 | P1 | R2 |
8Common mistakes
| Mistake | Why it is a problem |
|---|---|
| Confusing a hazard with a hazardous event | A hazard is an inherent property, such as high pressure; a hazardous event is an abnormal situation, such as tank rupture. Mixing them makes the causes inconsistent. |
| Rating only after measures | Without a before-measures rating, the actual effectiveness of barriers cannot be assessed and the most critical scenarios cannot be prioritised. |
| Extending a scale without extending the matrix | Adding a custom severity level, such as 5, without updating the criticality matrix leaves scenarios with no calculable risk level, as shown above. |
| Seeking exhaustiveness at the expense of perspective | PHA loses its purpose if it becomes FMEA in disguise. A broad overview is more useful, followed by deeper HAZOP or FMEA analysis of critical scenarios. |